Don't forget you can CLICK on a photo to view a larger image.

Go to January 2012

September 2012

The second vent was fitted; this time for the oven hood extractor. I was now ready to re-fit the weatherboarding.

(3rd September 2012)

August 2012 return to Latest News

The coloured glass panel above the door to the stairs on the ground floor.

(31st August 2012)

This commemorates the original build date.............

(31st August 2012)

......and the start of the rebuild.

(31st August 2012)

As viewed down the staircase.

(31st August 2012)

Installing the boiler flue vent; I had only screwed on some of the weatherboards pending establishing the vent positions.

(31st August 2012)

                                                                                                                                                                                go to September 2011

July 2012 back to top of page

Insulation complete to the rear wall of the cap.

(14th July 2012)

It was a very fiddly and time consuming job fitting all the battens as many had to have relieving saw cuts to enable them to bend.

(14th July 2012)

The frame for the door in the mill base taking shape in David's workshop.

(20th July 2012)

This door frame is somewhat larger than usual and will accomodate a double skinned door - opening shutter on the outside with glazed door inside.

(20th July 2012)

                                                                                                                                                                                      go to August 2011

June 2012 back to top of page

Insulating the rear wall of the cap.

(8th June 2012)

Slim battens were fitted either side of each rafter to allow for the plasterboard to be recessed and hence keep the rafters exposed.

(8th June 2012)

View to Leith hill tower from the fourth floor window - just where my desk will be!

(8th June 2012)

                                                                                                                                                                                                                 go to July 2011

May 2012 back to top of page

Detailed drawing of the fire-rated stair wall windows.

(Drawn on AutoCAD LT97)

These windows will let a little extra light from the window above into the dining room on the ground floor.

(5th May 2012)

Looking up the stairwell you can see similar windows opening out onto the first floor.

(8th May 2012)

Looking back down to the windows which open out onto the ground floor.

(8th May 2012)

The first floor windows in the side of the stairwell; iroko frames and fire resistant glass was used.

(8th May 2012)

                                                                                                                                                                                                                  go to June 2011

April 2012 back to top of page

The top layer of the floor insulation being layed in the granary.

(8th April 2012)

The granary floor insulation complete.

(14th April 2012)

Looking up the staircase to the fourth floor with the ballustrades just coming into view.

(20th April 2012)

Nearing the top............

(20th April 2012)

We will probably paint the ballustrades a bit darker so as to blend in more with the considerably exposed timberwork on this floor.

(20th April 2012)

                                                                                                                                                                                          go to May 2011

March 2012 back to top of page

The complicated stud work beneath the top staircase is many faceted as it winds around the tower.

(10th March 2012)

This shows the acoustic insulation and one of the service boards covering it up.

(10th March 2012)

The first layer of the granary floor insulation is complete.

(22nd March 2012)

                                                                                                                                                                                                                go to April 2011

February 2012 back to top of page

The comnpleted balustrade on the fourth floor.

(4th February 2012)

.......and from the top of the stairs.

(4th February 2012)

Starting to insulate the last floor in the tower.

(24th February 2012)

The cock-beaded panels lining the brickwork in the doorway out to the hall.

(24th February 2012)

                                                                                                                                                                                                             go to March 2011

January 2012 back to top of page

The airing cupboard in the bathroom, built over the stairwell.

(16th January 2012)

David completing the floor joisting out to the edge of the stairwell on the fourth floor.

(16th January 2012)

Detailed drawing of the ballustrade to be fitted on the fourth floor.

(Drawn on AutoCAD LT97)

A completed newel post; these are symbolic with the windmill at the bottom, grooves for each floor and finally the finial (from the top of cap).

(16th January 2012)

The machined handrail copied from our Edwardian one at home.

(19th January 2012)

One of the stair spindles, again with a representation of the windmill at the top and bottom.

(19th January 2012)

David turned all of the spindles and newel posts in his workshop.

(19th January 2012)

In between each spindle is a decorated partition (to give a sense of the ballastrades providing a wall).

(24th January 2012)

The insulation gathering momentum on the third floor.

(28th January 2012)

Ollie Coldman one of the decendants of the original builders' and subsequent millers' of the windmill.

(23rd April 2012)

                                                                                                                                                                                                            go to February 2011

                                                                                                                                                                                                         return to Latest News